Gas production in the next fiscal year (FY) 2015/2016 will not increase, according to a senior official at Egyptian Natural Gas Holding Company (EGAS).
The EGAS official added that maximum production will be 5 bcf/d, compared to 5.03 bcf/d in FY 2014/2015.
In a statement, the official said foreign companies postponed linking several new wells to production, waiting for re-pricing with the Egyptian government. The official added that the cost of drilling declined by roughly 50% as a result of the current lower rates for drilling rigs.
The official added that the lower prices of drilling rigs was due to sluggish demand abroad after they decreased the number of wells to be drilled annually, a result of the decline in international raw material prices.
The total number of postponed projects in foreign companies amounted to 1 bcf/d. The most prominent of these is Phase 9 of a British Petroleum (BP) project, whose production is at 500 mcf . The project was postponed to FY 2016/2017.
The official confirmed that the government has imported gas to cover the power plants’ needs since domestic production is in steady decline.
Egypt’s gas production declines by roughly 1.2 bcf annually at least, and most oil companies working in Egypt link wells to make up for the decline, instead of increasing production, the official said.
He also clarified that the average consumption of power plants during FY 2015/2016 will reach around 3.48 bcf/d of gas, compared to 3.23 bcf during the current FY 2014/2015.
The official added that gas consumption of other sectors will rise to 3.037 bcf daily, compared to about 2.74 bcf during FY 2014/2015. The EGAS official expected gas exports to halt completely next summer in accordance with the power plants’ needs.