Eni Secures Approval for Geliga Gas Development in Indonesia, Targeting 1 Bcf/d Production

Eni Secures Approval for Geliga Gas Development in Indonesia, Targeting 1 Bcf/d Production
Source: Eni Website

Eni has secured approval from Indonesian authorities for the Plan of Development (POD) for the Geliga gas field in the Kutei Basin, paving the way for the development of around eight trillion cubic feet (tcf) of gas resources across the Geliga and Gula fields, the company announced on November 23.

The approval, granted six months after the Geliga discovery, covers the development of 5.9 tcf of gas in place and 250 million barrels of associated condensate from Geliga, alongside 2.2 tcf of gas in place from the existing Gula discovery.

The integrated Geliga-Gula development is expected to reach peak production of one billion cubic feet per day (bcf/d) of gas and 50,000 barrels per day (bbl/d) of condensate, establishing a third production hub in the Kutei Basin, alongside the producing South Hub and the North Hub, which is currently under development.

Eni expects the three hubs to support gross production of approximately 3 bcf/d of gas and 140,000 bbl/d of condensate in East Kalimantan by the end of the decade, supplying both domestic and international markets.

The development will comprise 15 subsea wells, flowlines, and a newly built floating production, storage, and offloading (FPSO) vessel with processing capacity of approximately 1 bcf/d of gas and 80,000 bbl/d of condensate, alongside storage capacity of 1.4 million barrels.

Gas will be processed onboard the FPSO and transported through pipelines to the Santan Terminal and the East Kalimantan gas network. Some of the output will be liquefied at the Bontang LNG facility, while the remainder will be supplied to the domestic market. Stabilised condensate will be stored onboard the FPSO before being transferred to shuttle tankers.

The Geliga development will benefit from synergies with the North Hub project, which is expected to start operations in 2028. The integration is expected to reduce development costs and shorten execution timelines.

The Geliga development is operated by Searah, an independent upstream energy company established in June 2026 through a 50-50 strategic partnership between Eni and Malaysia’s PETRONAS.

Searah’s portfolio comprises 19 producing and development assets, including 14 in Indonesia and five in Malaysia. The company currently produces approximately 350,000 barrels of oil equivalent per day (kboe/d) and aims to exceed 500 kboe/d by 2028.