This Petrobel project includes upgrading of an existing obsolete control system at Petreco control room from single loop to control to DCS system, and also including field instruments replacement to cope with DCS.

Upgrading the following: 1-Extension of control room; 2- HAVC system upgrading; 3- Fuel gas system upgrading and install BMS for 6 heaters.

Phase I: Basic and detailed engineering
Phase II: Procurement and construction works
Project Status

Professional Services:
Phase I: Basic and detailed engineering activities were completed.
As built drawings for the existing plant & HAZOP works done by ENI in participation with Petrobel.
Phase II: Fax of awarding issued to Enppi on 04.02.2013 to execute the project in EPC basis, except procurement of heaters upgrading awarded to VERGA through Petrobel.

Procurement:
All P.O.’s were issued by Enppi as per schedule plus two P.O. issued by PTB related VERGA heaters and electrical cable.
All P.O.’s received at site.

Construction:
Civil works for control room extension and burner management system (BMS) building are in progress.
Construction actual progress achieved 73%.

Project Schedule:
Expected mechanically completion for phase-II May-2014.
Commissioning and start-up expected in October 2014.
Project’s actual progress achieved 67% versus 68% planned.